Marriott
Marriott Sugarland
Sugarland, TX · Renovation
Project Overview
Crews of 70+ phased work across an occupied site directly across from city hall, keeping the property in inventory through construction — and the brand walkthrough passed first inspection.
Scope of Work
Guest Rooms
300 rooms renovated top to bottom.
Timeline
Completed within 5 months while occupied.
Schedule
Completed 10 days ahead of original schedule.
Occupancy
100% during the duration of work. Keeping the property in inventory through construction.
Rework
Zero rework on this project.
Crew Size
70+ utilizing phased work process.